As part of an ongoing project, we loaded a shiploader in Antwerp for a mining project in Angola. The machine, measuring 63 x 19 x 27 meters, and weighing 330 ton, was lifted on board of vessel HHL Valparaiso, after driving alongside the vessel using SPMT. Together with the other equipment, including a reclaimer of 527 ton, all cargo will leave the port on board of the vessel, and will arrive in the port of Namibe about 18 days later, where we will discharge and organize the local storage of all equipment on the terminal. The crew, engineers, stevedores and representatives of manufacturers worked extremely hard and long hours these days, for a very technical job, and we are happy all large pieces were safely loaded. Many thanks to all involved in this !