Transport of 23 units sea fastening from Szcecin, Poland to Rotterdam on mv Peak Bilbao, and loading onto installation vessel Vole Au Vent, which will be used for the CVOW project offshore Virginia, US.
Recent Projects
Transition pieces for Taiwan
Transport of total 40 black steel TP of each 400 ton from Germany to Belgium in 14 voyages with Northern Rock and Arctic Rock. After completion of the TP’s, we will transport them to Flushing for onward delivery to a new windfarm in Taiwan.
Manora organized the transports, equipment and documentation.
Equipment for a offshore wind farm
Straddle Carriers transport
Transport of one of the largest land based cranes to Argentia
Over the last three months, Manora handled the transport of a large volume of project and crane equipment from Houston and Rotterdam to Argentia in Canada. The cargo, shipped in 19 different batches, using over 170 containers together with breakbulk shipments, will form a massive crane, one of the largest land-based cranes in the world. The crane will be used to safely and efficiently install fully assembled interior components at the West White Rose Project in Argentia
48 ton E Motor
Schottel on a containervessel
Offshore steel structures from Poland to Belgium
Steel to Cadiz and Sevilla
Transport of on offshore gripper frame
Manora Logistics transported a Gripper Frame from Szczecin, Poland to the Damen Yard in Rotterdam. The piece weighed 150 ton, and was approx 27 x 21 x 12,5 meters. After loading and skidding on board, the convoy departed under a beautiful blue sky, and the cargo was safely delivered a few days later. Great cooperation with the clients and all partners involved !
7 meter pieces to Gdansk
Ever seen 7 meter wide pieces on a flat rack ? Manora is shipping 45 x 40ft HC containers and 3 x 40ft flat rack with 7 meter wide pieces from Ex Works Dubai upto delivered Gdansk. The vessel Express Athens transported all units to Gdynia where the cargo was transhipped for final delivery to Gdansk.
Almost 100 containers project equipment to Poland
Impressive transport of two large leg frames
Survey Launch on the go
Two transports of heavy pumps
The first transport consisted of a 47,5 ton pump, 4,5 x 3,5 x 4,5 meters from Kinderdijk in The Netherlands, by barge to Antwerp, for transport on vessel ms “QIAN KUN” to Singapore.
A few weeks later we loaded another 2 dredging pumps, one of 125 ton and one of 150 ton, again onto a pontoon, transhipped the units on Chipolbrok CP SUN for shipment to Shanghai, after which we delivered the pumps to the shipyard in Dalian.
Transport of a tugboat
Steel sections for Windfarm in the UK
Manora transported large steel sections from Rotterdam to Ireland. The first unit of 460 ton steel was loaded at Rotterdam over a weekend. It was a challenging operation since the cargo was coated and had no fixed lashing points. But job completed and vessel Peak Breskens delivered the cargo safely. The week after the operation was repeated with Peak Bordeaux.
Gottwald Cranes between terminals
Transport of backhoe dredging equipment
Pipes and hoses off to Tema
Tugboat on the move in Asia
Transport of sections for a new concept of windfarm foundations to the UK
In three separate shipments we loaded first 2 bottom shafts, each approx 8,5 meter in diameter, later followed by two shipments of coated top sections, of which the heaviest unit weighed 457 ton, from the Netherlands to Ireland. After loading, lashing and securing the cargo in the port of Rotterdam, the vessels sailed for Belfast, where all pieces have been discharged at a private terminal, and used in a innovative windfarm project !
Offshore equipment to Rotterdam
Manora loaded at the Saipem Yard in Mekjarvik, Norway, 26 units offshore equipment, the largest one 5 meters high, the heaviest one 30 ton. These were trucked, loaded and shipped to Rotterdam, where we delivered all the different units to several locations in the Benelux by truck again. Many thanks for good cooperation with all parties involved